Voyager Energy Storage — Project Summary

Queue ID
CAISO-55041
Capacity
105.6 MW
Technology
Battery
Status
active
Location
Kern, CA
Region
CAISO
Developer
IA Status
Not Started

Voyager Energy Storage

BetaActiveBatteryCAISOLBNL

105.6 MW storage in Kern, CA · In queue since April 2023 · Proposed COD June 2027

105.6 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 2m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

CA

County

Kern

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

WHIRLWIND 230 kV

Data Source

LBNL

No news available for this project.