Castle Rock Energy Storage — Project Summary

Queue ID
CAISO-55036
Capacity
157.6 MW
Technology
Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
Not Started

Castle Rock Energy Storage

BetaActiveBatteryCAISOLBNL

157.6 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD December 2028

157.6 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 8m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

CA

County

San Bernardino

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

LUGO 500 kV

Data Source

LBNL