Glossy Garlic Solar
BetaActiveSolarBatteryCAISOLBNL
100 MW hybrid in Santa Clara, CA · In queue since April 2023 · Proposed COD March 2027
100 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 11m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-01
Technology
Solar50 MW · 50%
Battery50 MW · 50%
Project Details
State
CA
County
Santa Clara
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
LLAGAS 115 kV
Data Source
LBNL
No news available for this project.