Blue Oak Storage 2
608.44 MW storage in Alameda, CA · In queue since April 2023 · Proposed COD December 2031
608.44 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-12-31
State
CA
County
Alameda
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
TESLA-TRACY #1
Data Source
LBNL
After SMUD Pulls Out, Is the Coyote Creek Solar Project a Climate Win or a Loss?
Supporters cite emissions cuts, while critics say removing oak woodlands could undercut climate gains. Back Web Only Jan 28, 2026 By Jacob Peterson.
After SMUD Pulls Out, Is the Coyote Creek Solar Project a Climate Win or a Loss?
Supporters cite emissions cuts, while critics say removing oak woodlands could undercut climate gains. Back Web Only Jan 28, 2026 By Jacob Peterson.
After SMUD Pulls Out, Is the Coyote Creek Solar Project a Climate Win or a Loss?
Supporters cite emissions cuts, while critics say removing oak woodlands could undercut climate gains. Back Web Only Jan 28, 2026 By Jacob Peterson.
Renewable Energy Update 1.8.26
The Santa Cruz County Board of Supervisors on January 13 will review proposed rules governing large-scale battery energy storage systems...
Last updated 2026-03-26