MATTERHORN
BetaActiveSolarWindBatteryCAISOLBNL
1,215.27 MW hybrid in Riverside, CA · In queue since April 2023 · Proposed COD December 2029
1,215.27 MW
Capacity
3
Components
Solar + Wind + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 8m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-15
Technology
Solar404.892 MW · 33%
Wind404.28 MW · 33%
Battery406.098 MW · 33%
Project Details
State
CA
County
Riverside
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
DEVERS 500 kV
Data Source
LBNL