Redtail Energy Storage
BetaActiveBatteryCAISOLBNL
22.205 MW storage in Monterey, CA · In queue since April 2023 · Proposed COD October 2027
22.205 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 6m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
CA
County
Monterey
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Line: Soledad #2. Coordinates: (36.504994, -121.43843)
Data Source
LBNL
News & Articles (1)Beta