Separator Expansion — Project Summary

Queue ID
CAISO-54995
Capacity
12.5 MW
Technology
Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
Not Started

Separator Expansion

BetaActiveBatteryCAISOLBNL

12.5 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD June 2025

12.5 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 2m

Schedule

10 months past proposed COD

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-06

Project Details

State

CA

County

San Bernardino

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

ETIWANDA 230 kV

Data Source

LBNL