Jupiter Bowl
64.36 MW storage in Stanislaus, CA · In queue since April 2023 · Proposed COD June 2028
64.36 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
State
CA
County
Stanislaus
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
SALADO 115 kV
Data Source
LBNL
Energy Giant Proposes 10-Acre Battery Facility in Rural Hillsboro Next To Homes
A Texas-based energy developer, Jupiter Power LLC, has quietly filed plans with Washington County to build a massive 10-acre Battery Energy...
Energy Giant Proposes 10-Acre Battery Facility in Rural Hillsboro Next To Homes
A Texas-based energy developer, Jupiter Power LLC, has quietly filed plans with Washington County to build a massive 10-acre Battery Energy...
Energy Giant Proposes 10-Acre Battery Facility in Rural Hillsboro Next To Homes
A Texas-based energy developer, Jupiter Power LLC, has quietly filed plans with Washington County to build a massive 10-acre Battery Energy...
Energy Vault, Jupiter Power Announce Agreement for Additional 100 MW/200 MWh Battery Energy Storage System
WESTLAKE VILLAGE, Calif. & AUSTIN, Texas, June 04, 2025--Energy Vault Holdings Inc. (NYSE: NRGV) ("Energy Vault" or the "Company"),...
Last updated 2026-03-26