DT Solar
740.4 MW hybrid in Kings, CA · In queue since April 2023 · Proposed COD October 2030
740.4 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-10-01
State
CA
County
Kings
Region
CAISO
Developer
—
Utility
LSPC
Entity
CAISO
Point of Interconnection
MANNING 500 kV
Data Source
LBNL
‘Canada’s largest BESS’ at 1,858MWh begins construction, E-Storage is tech provider & EPC
E-Storage has been contracted to provide EPC services on the 411MW/1858MWh Skyview 2 BESS in Edwardsburgh Cardinal, Ontario, CA.
Lightsource bp starts building 562-MWh BESS at NSW solar farm
UK-based solar developer Lightsource bp said on Thursday it has started delivery of a 49-MW/562-MWh battery energy storage system (BESS) to...
Lightsource bp starts building 562-MWh BESS at NSW solar farm
UK-based solar developer Lightsource bp said on Thursday it has started delivery of a 49-MW/562-MWh battery energy storage system (BESS) to...
Lightsource bp starts building 562-MWh BESS at NSW solar farm
UK-based solar developer Lightsource bp said on Thursday it has started delivery of a 49-MW/562-MWh battery energy storage system (BESS) to...
Last updated 2026-03-26