Sunflower — Project Summary

Queue ID
CAISO-54903
Capacity
1434.8 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
Not Started

Sunflower

BetaActiveSolarBatteryCAISOLBNL

1,434.8 MW hybrid in San Bernardino, CA · In queue since April 2023 · Proposed COD March 2031

1,434.8 MW

Capacity

2

Components

Solar + Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

7y 11m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-03-01

Technology
Solar717.4 MW · 50%
Battery717.4 MW · 50%
Project Details

State

CA

County

San Bernardino

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

LUGO-PISGAH NO.2

Data Source

LBNL