Clay Flats Solar
BetaActiveBatteryCAISOLBNL
434.24 MW storage in Kings, CA · In queue since April 2023 · Proposed COD October 2030
434.24 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 6m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-10-01
Project Details
State
CA
County
Kings
Region
CAISO
Developer
—
Utility
LSPC
Entity
CAISO
Point of Interconnection
MANNING 500 kV
Data Source
LBNL