Stanley — Project Summary

Queue ID
CAISO-54882
Capacity
2070.9121 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
CAISO
Developer
IA Status
Not Started

Stanley

BetaActiveSolarBatteryCAISOLBNL

2,070.912 MW hybrid in Maricopa, AZ · In queue since April 2023 · Proposed COD April 2030

2,070.912 MW

Capacity

2

Components

Solar + Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7 years

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-04-30

Technology
Solar1,038.8 MW · 50%
Battery1,032.112 MW · 50%
Project Details

State

AZ

County

Maricopa

Region

CAISO

Developer

Utility

DCRT

Entity

CAISO

Point of Interconnection

CIELO AZUL 500 kV

Data Source

LBNL