Saltgrass — Project Summary

Queue ID
CAISO-54873
Capacity
171.297 MW
Technology
Battery
Status
active
Location
Stanislaus, CA
Region
CAISO
Developer
IA Status
Not Started

Saltgrass

BetaActiveBatteryCAISOLBNL

171.297 MW storage in Stanislaus, CA · In queue since April 2023 · Proposed COD January 2026

171.297 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 9m

Schedule

2 months past proposed COD

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-30

Project Details

State

CA

County

Stanislaus

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

SALADO 115 kV

Data Source

LBNL

No news available for this project.