Saltgrass
BetaActiveBatteryCAISOLBNL
171.297 MW storage in Stanislaus, CA · In queue since April 2023 · Proposed COD January 2026
171.297 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 9m
Schedule
2 months past proposed COD
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-30
Project Details
State
CA
County
Stanislaus
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
SALADO 115 kV
Data Source
LBNL
No news available for this project.