Solstice C
420 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD May 2031
420 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-01
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
LSPC
Entity
CAISO
Point of Interconnection
MANNING 500 kV
Data Source
LBNL
Renewable America’s Community Solar Project Goes Live, Bringing Affordable Energy To Low-Income Households
Discover Renewable America's West Tambo Clean Power II project, contributing clean energy and sustainability to California communities.
Renewable America’s Community Solar Project Goes Live, Bringing Affordable Energy To Low-Income Households
Discover Renewable America's West Tambo Clean Power II project, contributing clean energy and sustainability to California communities.
Last updated 2026-03-26