Green Palms
306.6 MW generation in Riverside, CA · In queue since April 2023 · Proposed COD December 2030
306.6 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
State
CA
County
Riverside
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
COLORADO RIVER 230 kV
Data Source
LBNL
California’s wind and solar projects face new federal hurdles
11 solar projects and one onshore wind project now face potential delays or cancellation, according to an analysis of federal data by Atlas Public Policy.
Cadiz Inks New Energy Contract
Downtown-based Cadiz agrees to allow a renewable energy company to add solar generation and hydrogen production to its Cadiz Ranch campus.
Solar Is Booming in the California Desert, if Water Issues Don’t Get in the Way
DESERT CENTER, Calif.—Solar farms stretch out mile after mile along Interstate 10 around Palm Springs, creating one of the densest areas of...
Last updated 2026-03-26