Township Power Bank Expansion
BetaActiveGasBatteryCAISOLBNL
22.6 MW hybrid in Sutter, CA · In queue since April 2023 · Proposed COD June 2028
22.6 MW
Capacity
2
Components
Gas + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 2m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01
Technology
Gas11.3 MW · 50%
Battery11.3 MW · 50%
Project Details
State
CA
County
Sutter
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
GREENLEAF #1 TAP
Data Source
LBNL
No news available for this project.