Coriander
BetaActiveSolarBatteryCAISOLBNL
61.952 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD April 2029
61.952 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6 years
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-02
Technology
Solar30.976 MW · 50%
Battery30.976 MW · 50%
Project Details
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
CRESCENT SW STA 70 kV
Data Source
LBNL
No news available for this project.