Argos Solar — Project Summary

Queue ID
CAISO-54767
Capacity
705.8873 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
Not Started

Argos Solar

BetaActiveSolarBatteryCAISOLBNL

705.887 MW hybrid in San Bernardino, CA · In queue since April 2023 · Proposed COD June 2030

705.887 MW

Capacity

2

Components

Solar + Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7y 2m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-06-01

Technology
Solar352.25 MW · 50%
Battery353.637 MW · 50%
Project Details

State

CA

County

San Bernardino

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

CALCITE 230 kV

Data Source

LBNL

No news available for this project.