Onyx — Project Summary

Queue ID
CAISO-54765
Capacity
353.1115 MW
Technology
Solar+Battery
Status
active
Location
Clark, NV
Region
CAISO
Developer
IA Status
Not Started

Onyx

BetaActiveSolarBatteryCAISOLBNL

353.112 MW hybrid in Clark, NV · In queue since April 2023 · Proposed COD December 2030

353.112 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Not Started

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7y 8m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-02

Project Details

State

NV

County

Clark

Region

CAISO

Developer

Utility

GLW

Entity

CAISO

Point of Interconnection

DESERT VIEW-INNOVATION

Data Source

LBNL