Onyx
BetaActiveSolarBatteryCAISOLBNL
353.112 MW hybrid in Clark, NV · In queue since April 2023 · Proposed COD December 2030
353.112 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Not Started
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 8m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-12-02
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
DESERT VIEW-INNOVATION
Data Source
LBNL