Charros Energy Center — Project Summary

Queue ID
CAISO-54760
Capacity
619.2 MW
Technology
Solar+Battery
Status
active
Location
Yuba, CA
Region
CAISO
Developer
IA Status
Not Started

Charros Energy Center

BetaActiveSolarBatteryCAISOLBNL

619.2 MW hybrid in Yuba, CA · In queue since April 2023 · Proposed COD July 2028

619.2 MW

Capacity

2

Components

Solar + Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 3m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-31

Technology
Solar105 MW · 17%
Battery514.2 MW · 83%
Project Details

State

CA

County

Yuba

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Rio Oso-Colgate & Rio Oso-Round Mountain T-Line

Data Source

LBNL

No news available for this project.