Stable
747.84 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD May 2031
747.84 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-01
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
LSPC
Entity
CAISO
Point of Interconnection
MANNING 500 kV
Data Source
LBNL
PowerBank Moves Ahead With Landfill-Based Community Solar Project in New York
Detailed price information for Powerbank Corporation (SUUN-Q) from The Globe and Mail including charting and trades.
China's energy regulator says to build new power system
China will build a new, diversified clean energy system and work to keep global new energy industry supply chains stable, Wan Jinsong,...
How Ormat's (ORA) Stable Base and Storage Growth Support UBS's Bullish View
Ormat Technologies, Inc. (NYSE:ORA) is one of the 10 Best Renewable Energy Stocks to Buy Now. As of March 8, 2026, Wall Street's consensus...
Handcrafted micro hydroelectric power plant with aluminum Pelton wheel overcomes pressure challenge and demonstrates stable operation, paving the way for efficiency gains with injector nozzle.
A handcrafted micro-hydroelectric power plant underwent continuous operation tests and demonstrated stable performance. The highlight of the...
Last updated 2026-03-26