Hillside Energy Storage
BetaActiveBatteryCAISOLBNL
1,041.037 MW storage in Los Angeles, CA · In queue since April 2023 · Proposed COD June 2029
1,041.037 MW
Capacity
2
Components
Battery + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 2m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-01
Technology
Battery2.74 MW · 0%
Battery1,038.297 MW · 100%
Project Details
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
VINCENT 230 kV
Data Source
LBNL
No news available for this project.