Coyote Ranch Energy Storage — Project Summary

Queue ID
CAISO-54699
Capacity
415.76992 MW
Technology
Battery
Status
active
Location
San Joaquin, CA
Region
CAISO
Developer
IA Status
Not Started

Coyote Ranch Energy Storage

BetaActiveBatteryCAISOLBNL

415.77 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD June 2029

415.77 MW

Capacity

2

Components

Battery + Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

6y 2m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-06-01

Technology
Battery2.74 MW · 1%
Battery413.03 MW · 99%
Project Details

State

CA

County

San Joaquin

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

LOCKEFORD 230 kV

Data Source

LBNL

No news available for this project.