Energia Sierra Juarez 4
BetaActiveWindCAISOLBNL
309.353 MW generation in Tijuana, MX · In queue since April 2023 · Proposed COD March 2030
309.353 MW
Capacity
1
Components
Wind
2y 11m
In Queue
Not Started
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 11m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-03-31
Project Details
State
MX
County
Tijuana
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
EAST COUNTY 230 kV
Data Source
LBNL
No news available for this project.