Reflex — Project Summary

Queue ID
CAISO-54672
Capacity
129.1 MW
Technology
Solar
Status
active
Location
Riverside, CA
Region
CAISO
Developer
IA Status
Not Started

Reflex

BetaActiveSolarCAISOLBNL

129.1 MW generation in Riverside, CA · In queue since April 2023 · Proposed COD January 2029

129.1 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Not Started

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 9m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-01

Project Details

State

CA

County

Riverside

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

RED BLUFF 230 kV

Data Source

LBNL