Nelson Hills
204.57 MW generation in Nye, NV · In queue since April 2023 · Proposed COD June 2031
204.57 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-01
State
NV
County
Nye
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
VALLEY SWITCH 230 kV
Data Source
LBNL
First Nations in oil country are converting old wells to geothermal
First Nations, Inuit and Métis people are already at the forefront of the energy transition in Canada. Geothermal offers a new opportunity.
Northern Nevada's Largest Solar Project Set to Power-Up
Construction continues on northern Nevada's largest solar project. The Turquoise Solar Project is set to electrify its first phase next...
Last updated 2026-03-26