Serenity — Project Summary

Queue ID
CAISO-54669
Capacity
305.4 MW
Technology
Solar
Status
active
Location
Nye, NV
Region
CAISO
Developer
IA Status
Not Started

Serenity

BetaActiveSolarCAISOLBNL

305.4 MW generation in Nye, NV · In queue since April 2023 · Proposed COD June 2031

305.4 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Not Started

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

8y 2m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-06-01

Project Details

State

NV

County

Nye

Region

CAISO

Developer

Utility

GLW

Entity

CAISO

Point of Interconnection

VALLEY SWITCH 230 kV

Data Source

LBNL