Shoestring
280 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD May 2031
280 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-01
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
LSPC
Entity
CAISO
Point of Interconnection
MANNING 500 kV
Data Source
LBNL
Meet Your Neighborhood Greenhouse Gas Emitters
With a drought and its resultant fires ongoing across the state, The Shoestring looks into the biggest emitters in western Mass.
Meet Your Neighborhood Greenhouse Gas Emitters
With a drought and its resultant fires ongoing across the state, The Shoestring looks into the biggest emitters in western Mass.
Meet Your Neighborhood Greenhouse Gas Emitters
With a drought and its resultant fires ongoing across the state, The Shoestring looks into the biggest emitters in western Mass.
Meet Your Neighborhood Greenhouse Gas Emitters
With a drought and its resultant fires ongoing across the state, The Shoestring looks into the biggest emitters in western Mass.
Last updated 2026-03-26