Bolt
525 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD May 2031
525 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-01
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
LSPC
Entity
CAISO
Point of Interconnection
MANNING 500 kV
Data Source
LBNL
Norton Rose Fulbright advises on winning ‘deals of the year’ at Project Finance International Awards
Global law firm Norton Rose Fulbright has advised on multiple winning deals across the Americas, Africa, Europe and Asia Pacific at this year's Project...
From Sea to Shining Sea: A Recap of 2025 State Solar Policy Wins
Here's an update from the Solar Energy Industries Association (SEIA) on its state policy wins in 2025 and what comes next:.
Last updated 2026-03-26