Fornax — Project Summary

Queue ID
CAISO-54643
Capacity
206.25 MW
Technology
Solar+Battery
Status
active
Location
Fresno, CA
Region
CAISO
Developer
IA Status
Not Started

Fornax

BetaActiveSolarBatteryCAISOLBNL

206.25 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD December 2031

206.25 MW

Capacity

2

Components

Solar + Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

8y 8m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-12-01

Technology
Solar103.125 MW · 50%
Battery103.125 MW · 50%
Project Details

State

CA

County

Fresno

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

TRANQUILLITY SW STA 230 kV

Data Source

LBNL

No news available for this project.