Tobin
509.49 MW hybrid in Los Angeles, CA · In queue since April 2023 · Proposed COD April 2030
509.49 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-04-30
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
ANTELOPE-WHIRLWIND
Data Source
LBNL
Murray Lyons: Build Saskatchewan’s big reactors on Codette Lake or Tobin Lake
Working for Saskatoon-based uranium giant Cameco Corporation for eight years provided this former business journalist many insights into the...
Murray Lyons: Build Saskatchewan’s big reactors on Codette Lake or Tobin Lake
Working for Saskatoon-based uranium giant Cameco Corporation for eight years provided this former business journalist many insights into the...
Gilbert + Tobin advises Aitken Mount on landmark $600 million NexGen Energy placement as uranium sector heats up
Gilbert + Tobin has advised Aitken Mount, as underwriter and joint lead manager, on NexGen Energy Ltd's (ASX: NXG; TSX/NYSE: NXE) $600...
Isabella, DTE celebrate solar park construction
If it wasn't for the mud on Crawford Road and the traffic on Mission, Isabella County Commission Chairman Tobin Hope would have ridden his...
Last updated 2026-03-26