Connor
514.8 MW storage in Los Angeles, CA · In queue since April 2023 · Proposed COD April 2030
514.8 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-04-30
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
VINCENT 500 kV
Data Source
LBNL
Surge Announces Former Berkshire Hathaway Energy Executive Mr. Richard Weech Joins the Board as an Independent Director
West Vancouver, British Columbia--(Newsfile Corp. - March 17, 2026) - Surge Battery Metals Inc. TSXV:NILI (OTCQX: NILIF) (FSE: DJ5) (the...
Surge Announces Former Berkshire Hathaway Energy Executive Mr. Richard Weech Joins the Board as an Independent Director
West Vancouver, British Columbia--(Newsfile Corp. - March 17, 2026) - Surge Battery Metals Inc. TSXV:NILI (OTCQX: NILIF) (FSE: DJ5) (the...
Surge Announces Former Berkshire Hathaway Energy Executive Mr. Richard Weech Joins the Board as an Independent Director
West Vancouver, British Columbia--(Newsfile Corp. - March 17, 2026) - Surge Battery Metals Inc. TSXV:NILI (OTCQX: NILIF) (FSE: DJ5) (the...
Surge Announces Former Berkshire Hathaway Energy Executive Mr. Richard Weech Joins the Board as an Independent Director
West Vancouver, British Columbia--(Newsfile Corp. - March 17, 2026) - Surge Battery Metals Inc. TSXV:NILI (OTCQX: NILIF) (FSE: DJ5) (the...
Last updated 2026-03-26