Sergio Storage
199 MW storage in Orange, CA · In queue since April 2023 · Proposed COD May 2028
199 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-03
State
CA
County
Orange
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
VILLA PARK 230 kV
Data Source
LBNL
The Hydrogen Stream: Verna completes first two hydrogen pilot wells in Canada
Vema Hydrogen has completed two pilot hydrogen wells in Quebec, Canada, while Advait Greenergy and InSolare Energy are moving forward on...
Tesla signs massive 1 GWh Megapack project in the UK with Matrix Renewables
Tesla Energy has secured another massive Megapack project in the UK. Matrix Renewables announced today that it has signed a full EPC...
CAF grants loan to boost energy transition of ENGIE Chile
The financing will accelerate ENGIE Chile's investment plan, contributing to the decarbonization of the Chilean electricity sector.
CAF grants loan to boost energy transition of ENGIE Chile
The financing will accelerate ENGIE Chile's investment plan, contributing to the decarbonization of the Chilean electricity sector.
Last updated 2026-03-26