Great Dane Solar
1,200 MW hybrid in Kern, CA · In queue since April 2023 · Proposed COD October 2028
1,200 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Manning-Midway 500 kV Line
Data Source
LBNL
Wisconsin utilities partner again to purchase solar and storage capacity from Invenergy
Wisconsin utility MGE is partnering with We Energies and WPS to purchase 30MW of solar capacity and 16.5MW of battery storage from...
Wisconsin utilities partner again to purchase solar and storage capacity from Invenergy
Wisconsin utility MGE is partnering with We Energies and WPS to purchase 30MW of solar capacity and 16.5MW of battery storage from...
Wisconsin utilities partner again to purchase solar and storage capacity from Invenergy
Wisconsin utility MGE is partnering with We Energies and WPS to purchase 30MW of solar capacity and 16.5MW of battery storage from...
Wisconsin utilities partner again to purchase solar and storage capacity from Invenergy
Wisconsin utility MGE is partnering with We Energies and WPS to purchase 30MW of solar capacity and 16.5MW of battery storage from...
Last updated 2026-03-26