Chance Solar
1,789.991 MW hybrid in Nye, NV · In queue since April 2023 · Proposed COD October 2028
1,789.991 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
State
NV
County
Nye
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
BEATTY 230kV
Data Source
LBNL
Feds Cancel 6.2-GW Nevada Solar Plant OK in Latest Barrage of Anti-renewables Crusade
Esmeralda Seven's multiple projects now must seek separate approvals to proceed, as administration expands list of renewables targeted for...
Wait, The Gigantic Esmeralda 7 Solar Power Project Is Not Dead — Yet
Rumors of the death of the Esmeralda 7 solar power and energy storage projects in Nevada have been greatly exaggerated, for the time being.
Trump officials cancel major solar project in latest hit to renewable energy
Esmeralda 7 in Nevada would have produced enough energy to power 2m homes.
NV Energy's bill pricing switch, Greenlink construction costs OK'd by regulators
Starting in April, all Southern Nevada NV Energy customers, including those who have solar, will have a new billing structure that will...
Last updated 2026-03-26