Borderline Solar — Project Summary

Queue ID
CAISO-54571
Capacity
1267.6589 MW
Technology
Solar+Battery
Status
active
Location
Inyo, CA
Region
CAISO
Developer
IA Status
Not Started

Borderline Solar

BetaActiveSolarBatteryCAISOLBNL

1,267.659 MW hybrid in Inyo, CA · In queue since April 2023 · Proposed COD October 2028

1,267.659 MW

Capacity

2

Components

Solar + Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 6m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-01

Technology
Solar638.044 MW · 50%
Battery629.615 MW · 50%
Project Details

State

CA

County

Inyo

Region

CAISO

Developer

Utility

GLW

Entity

CAISO

Point of Interconnection

TROUT CANYON 230 kV

Data Source

LBNL