Lycan Solar 2
192.491 MW generation in Riverside, CA · In queue since April 2023 · Proposed COD October 2028
192.491 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
State
CA
County
Riverside
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
RED BLUFF 500 kV
Data Source
LBNL
Sol Systems Acquires Wolf Creek Renewable Energy Center in Saline County, Illinois
Washington, D.C.--(Newsfile Corp. - March 13, 2026) - Sol Systems, a leading national clean energy developer and independent power producer...
Sol Systems Acquires Wolf Creek Renewable Energy Center in Saline County, Illinois
Washington, D.C.--(Newsfile Corp. - March 13, 2026) - Sol Systems, a leading national clean energy developer and independent power producer...
Sol Systems Acquires Wolf Creek Renewable Energy Center in Saline County, Illinois
Washington, D.C.--(Newsfile Corp. - March 13, 2026) - Sol Systems, a leading national clean energy developer and independent power producer...
Sol Systems Acquires Wolf Creek Renewable Energy Center in Saline County, Illinois
Washington, D.C.--(Newsfile Corp. - March 13, 2026) - Sol Systems, a leading national clean energy developer and independent power producer...
Last updated 2026-03-26