Calypso Solar 2 — Project Summary

Queue ID
CAISO-54565
Capacity
407.8171 MW
Technology
Solar
Status
active
Location
Riverside, CA
Region
CAISO
Developer
IA Status
Not Started

Calypso Solar 2

BetaActiveSolarCAISOLBNL

407.817 MW generation in Riverside, CA · In queue since April 2023 · Proposed COD October 2028

407.817 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Not Started

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 6m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-01

Project Details

State

CA

County

Riverside

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

COLORADO RIVER 500 kV

Data Source

LBNL

No news available for this project.