Egret
BetaActiveSolarBatteryCAISOLBNL
1,701.56 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD September 2028
1,701.56 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 5m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Technology
Solar1,055.56 MW · 62%
Battery646 MW · 38%
Project Details
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
LSPC
Entity
CAISO
Point of Interconnection
MANNING 500 kV
Data Source
LBNL
No news available for this project.