Ramos
260 MW hybrid in Merced, CA · In queue since April 2023 · Proposed COD March 2028
260 MW
Capacity
2
Components
Gas + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-31
State
CA
County
Merced
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
LOS BANOS 230 kV
Data Source
LBNL
These Bronx Tenants Lived Six Weeks Without Water and Power. The City’s Fix? A Vacate Order
The plight of the Ramos family reveals the weaknesses in the City's system to protect tenants from unlivable conditions—and from being put...
Aboitiz Power building 30-MW energy storage in Cebu
Aboitiz Power Corp. will develop a 30-megawatt (MW) hybrid battery energy storage system (BESS) at Mactan Economic Zone in Cebu,
Home microgrids: a blueprint for the future of sustainable household energy?
Nestled between a spruce hedge and a hazel hurdle fence on Stone Edge Farm, a 16-acre estate in Sonoma County, Northern California that has...
P.E.I. project that's recording Island bat population is hearing grounds for optimism
Watershed groups have been using acoustic monitoring to track the Island's bat population, including in old sandstone wells that have been...
Last updated 2026-03-26