Sevillano — Project Summary

Queue ID
CAISO-54537
Capacity
305.15 MW
Technology
Solar
Status
active
Location
Tehama, CA
Region
CAISO
Developer
IA Status
Not Started

Sevillano

BetaActiveSolarCAISOLBNL

305.15 MW generation in Tehama, CA · In queue since April 2023 · Proposed COD June 2028

305.15 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Not Started

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 2m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

Project Details

State

CA

County

Tehama

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

COTTONWOOD-LOGAN CREEK

Data Source

LBNL

No news available for this project.