Rover
206.2 MW storage in Los Angeles, CA · In queue since April 2023 · Proposed COD June 2028
206.2 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
VINCENT 230 kV
Data Source
LBNL
Nevada’s Lithium Could Help Save the Earth. But What Happens to Nevada? (Published 2025)
Many climate experts see its deserts as a place to build the green-energy future. For two local activists, the price is too great.
JLR, Allye Energy partner on 270 kWh portable battery energy storage system
Jaguar Land Rover (JLR) and Allye Energy have agreed to collaborate on a 270 kWh portable battery energy storage system (BESS) built with second-life Range...
Michigan residents on pipeline route face eminent domain lawsuit
ET Rover Pipeline is ready to start building a natural-gas pipeline, through Livingston, Washtenaw and Lenawee counties.
Last updated 2026-03-26