POTENTIA-VIRIDI 2
BetaActiveBatteryCAISOLBNL
405.289 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD December 2028
405.289 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 8m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-15
Project Details
State
CA
County
San Joaquin
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
TESLA 500 kV
Data Source
LBNL