Broadview
1,294.64 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD September 2028
1,294.64 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
LOS BANOS-GATES #3 (PGAE Portion Only)
Data Source
LBNL
How a company quietly acquired 5,100 acres for a data center in Eastern Montana
When a little-known company called Montana Property LLC purchased 5,000 acres — around eight square miles — just south of Broadview in 2024,...
How a company quietly acquired 5,100 acres for a data center in Eastern Montana
When a little-known company called Montana Property LLC purchased 5,000 acres — around eight square miles — just south of Broadview in 2024,...
Here's where to expect a potential Yellowstone County data center
In 2024, Montana Property LLC purchased 20 parcels — or eight square miles — of arid, agricultural land south of Broadview in Yellowstone...
Here's where to expect a potential Yellowstone County data center
In 2024, Montana Property LLC purchased 20 parcels — or eight square miles — of arid, agricultural land south of Broadview in Yellowstone...
Last updated 2026-03-26