Lagunez
BetaActiveSolarBatteryCAISOLBNL
402.6 MW hybrid in Merced, CA · In queue since April 2023 · Proposed COD November 2029
402.6 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 7m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-11-01
Technology
Solar251.7 MW · 63%
Battery150.9 MW · 37%
Project Details
State
CA
County
Merced
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
POLE LINE 230 kV
Data Source
LBNL