Alisa Solar Energy Complex 2
BetaActiveSolarBatteryCAISOLBNL
1,000 MW hybrid in Yuma, AZ · In queue since April 2023 · Proposed COD June 2030
1,000 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 2m
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-01
Technology
Solar500 MW · 50%
Battery500 MW · 50%
Project Details
State
AZ
County
Yuma
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
NORTH GILA - HOODOO WASH (SDGE Portion Only)
Data Source
LBNL
No news available for this project.