RIGHTEOUS ENERGY STORAGE
500 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD May 2030
500 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-05-27
State
CA
County
San Bernardino
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
LUGO 500 kV
Data Source
LBNL
Texas company eyes former Vermont Yankee site for battery energy storage system
Representatives from PowerTransitions have been meeting with officials in Vernon about potentially developing the 140-acre site along the...
Texas company eyes former Vermont Yankee site for battery energy storage system
Representatives from PowerTransitions have been meeting with officials in Vernon about potentially developing the 140-acre site along the...
Green Mountain Power seeks to install up to 1,200 storage batteries in remote homes
The state's largest electric utility is asking state regulators to approve a new tariff for all its ratepayers that would fund a project to...
Green Mountain Power seeks to install up to 1,200 storage batteries in remote homes
The state's largest electric utility is asking state regulators to approve a new tariff for all its ratepayers that would fund a project to...
Last updated 2026-03-26