CROW CREEK SOLAR 1 (FKA: FRONTIER SOLAR 1) (FKA AS SCATEC WESTSIDE SOLAR RANCH I AND STANISLAUS PV - PHASE 1)
BetaActiveSolarBatteryCAISOLBNL + Live
40 MW hybrid in Stanislaus, CA · In queue since December 2009 · Proposed COD April 2025
40 MW
Capacity
2
Components
Solar + Battery
16y 3m
In Queue
IA Executed
IA Status
Signed Jul 2011
Interconnection Timeline
Queue → IA
1y 7m
IA → COD
13y 9m
Total Duration
1y 7m
Schedule
12 months past proposed COD
Construction75%
Queue EntryDec 18, 2009
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJul 1, 2011
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-04-01
Technology
Solar20 MW · 50%
Battery20 MW · 50%
Project Details
State
CA
County
Stanislaus
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Salado-Newman #1 60kV Line
Data Source
LBNL + Live
No news available for this project.