ROSAMOND WEST SOLAR
BetaActiveSolarBatteryCAISOLBNL + Live
447.3 MW hybrid in Kern, CA · In queue since July 2009 · Proposed COD March 2029
447.3 MW
Capacity
2
Components
Solar + Battery
16y 8m
In Queue
IA Executed
IA Status
Signed Aug 2020
Interconnection Timeline
Queue → IA
11y 1m
IA → COD
8y 7m
Total Duration
11y 1m
Construction75%
Queue EntryJul 31, 2009
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementAug 5, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2029-03-31
Technology
Solar299.6 MW · 67%
Battery147.7 MW · 33%
Project Details
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Whirlwind Substation 230kV
Data Source
LBNL + Live
No news available for this project.