LOS ESTEROS CRITICAL ENERGY FACILITY EXPANSION — Project Summary

Queue ID
CAISO-378
Capacity
123 MW
Technology
Battery
Status
active
Location
Santa Clara, CA
Region
CAISO
Developer
IA Status
IA Executed

LOS ESTEROS CRITICAL ENERGY FACILITY EXPANSION

BetaActiveGasBatteryCAISOLBNL + Live

123 MW hybrid in Santa Clara, CA · In queue since May 2008 · Proposed COD September 2023

123 MW

Capacity

2

Components

Gas + Battery

17y 10m

In Queue

IA Executed

IA Status

Signed Apr 2011

Interconnection Timeline

Queue → IA

2y 11m

IA → COD

12y 5m

Total Duration

2y 11m

Schedule

31 months past proposed COD

Construction75%
Queue EntryMay 28, 2008

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementApr 4, 2011

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2023-09-01

Technology
Gas120 MW · 98%
Battery3 MW · 2%
Project Details

State

CA

County

Santa Clara

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Los Esteros 115 kV

Data Source

LBNL + Live

No news available for this project.